Dubai LRT Viaduct Span by Span Erection Method
Dubai LRT Viaduct Span by Span Erection Method
Dubai LRT Viaduct Span by Span Erection Method
Freysa-Freyssinet,
F.Kerim Gkay Cad. Poyraz Sok. Tunludemir Plaza, No 5/5
Hasapnaa / Kadky / stanbul - TRKYE
Tel: (216) 349 87 75
E-Posta: [email protected]
Summary
This article presents the bridge construction techniques carried out for Dubai light rail
transit system red and green lines viaducts. After an overview of the whole project,
more than 70 km of metro line and 43 stations, we will focus on the elevated viaduct
part which represents 75% the project length, more than 52 km of viaduct.
Chosen bridge construction technique had to meet several requirements due to
numerous constraints, among which speed of construction, geometry adjustability,
environment disturbance. These project constraints led to use precast segmented span
by span erection method. This construction method is the optimal one in terms of
construction speed, quantity optimization, construction quality and risk management.
On particular locations where constraints obliged to have longer span lengths, balanced
cantilever erection precast segments have been used, combining the advantage of
precast segment bridge (speed of construction) with balanced cantilever method
advantages (longer spans).
Key words
Metro rail bridge, span-by-span construction method, U shape precast segment, selflaunching erection gantry, post-tensioning
The Project:
Dubai Municipality identified the need for a rail system to relieve growing motor traffic
and support continuing urban development based on studies that began in 1997. Systra
was awarded the preliminary engineering contract, and Dubai Rail Link (DURL)
Consortium, a consortium of five companies consisting of Mitsubishi Heavy Industries
(MHI), Mitsubishi Corporation, Obayashi Corporation and Kajima Corporation from
Japan and Yapi Merkezi from Turkey, has undertaken the first two lines of the high-tech
driverless rapid transit system (Red and Green lines) on a design and build scheme in
July 2005.
The metro will be fully integrated within the road network operated by the Roads &
Transport Authority (RTA), a body created in late 2005. The projects ownership,
including future rail lines to be constructed, has also been transferred to RTA in
November 2005. Routes will be organized around the backbone provided by the rail
system.
Around 1.74 million passengers used the metro in its first month, according to the
statistics released by the RTA. The average number of passengers travelling on the Red
Line has recently exceeded 140,000 per day.
Red Line (52.1 km) has commenced in August 2005 and Green Line (22.6 km), which
intersects the Red Line at two stations, in July 2006. Red Line has been opened into
commercial operation on 09 September 2009, a famous target date (09.09.09) set at the
very beginning, and Green Line will be handed over to RTA on 15 August 2011.
52.1 km (32.5 miles) long Red Line will have 29 stations, four of which will be
underground. It will run from Rashidiva to Jebel Ali passing through Dubai Airport and
the American University of Dubai. The whole 52.1km is expected to take 60 minutes.
22.7 km (14.2 miles) long Green Line will have 18 stations six underground and 12 at
ground level. Interchange stations with Red Line will be built at Union Square and
Burjuman with direct connections to the Red Line.
The 52.1 km of the Red line is composed of:
- 5.5 km of tunnel ( including 4 underground stations)
- 43 km of elevated viaducts
- 3.5 km of at-grade section viaducts
The 22.7 km of the Green line is composed of:
- 7.6 km of tunnel ( including 6 underground stations)
- 15.0 km of elevated viaducts
- 0.6 km of at-grade section viaducts
Picture 1: Dubai Metro Project Red & Green line plan view
Project organisation:
The Owner is Roads & Transport Authority. The Engineer appointed by the Owner is
Systra-Parsons JV. The Main Contractor for the Metro civil works is JAPAN-TURKEY
Metro JV, a Joint Venture between Obayashi Corporation, Kajima Corporation and
Yapi Merkezi. The main contractor is a part of DURL Consortium with Mitsubishi
Heavy Industries and Mitsubishi Corporation.
JAPAN-TURKEY Metro JV has subcontracted elevated viaduct erection works to a
joint venture, called VFR, between Freyssinet (France), VSL (Switzerland) and Rizzani
De Eccher (Italy).
Elevated structure overview:
VFR has been responsible for elevated viaduct erection using segmental bridge
technology, including precasting of all segments and their erection based on 3
construction methods:
- Erection by means of launching gantry
- Erection on falsework
- Cantilever erection
Unit
RED LINE
T1 / T3
GREEN LINE
span unit
1.012
24
325
1.361
span unit
span unit
38
66
58
22
26
118
92
span unit
73
47
120
span unit
12
15
span unit
Unit
segment
unit
meter
48
1.249
82
24
447
72
1.778
11.730
45.035
576
1.926
4.163
9.434
16.469
56.395
TOTAL
More than 90% of elevated viaducts have been installed using span by span erection
method. All segments installed using this method are U-shaped.
=> none
alignment,
only on
pier
As precised in table 1 here above more than 16.400 units of segments has been
precasted in less than 2 years.
For logistic purpose a dedicated precasting yard has been installed in Dubai in order to
feed erection process in the requested time.
Precasting Yard
Due to the required number of segment, a precasting yard dedicated only to this Project
has been able to be installed not far from erection site, out of city down town, in Jebel
Ali. The casting yard laid over a total area of 540,000m2.
This area contained:
- 9 tower cranes for displacement of reinforcement cages form rebars jigs to
casting moulds
- 11 gantry cranes for transport or casted segment from moulds to storage area
- 42 forms for iso segment casting
- 11 forms balanced cantilever segment casting
- 7 forms for segments T1/T3 segment casting
- 2.500 segment storage capacity
- 44 segment segment max. daily production capacity
- 985 segment segment max. monthly production capacity
- 780 employees (including 67 staff)
- Offices and personnel camp.
Match casting technique has been used on this Project to ensure a severe geometry
control.
First, segment reinforcement is preassembled on rebar jig. After a first control,
reinforcement cage, including post tensioning ducts, is installed in the casting form by
means of tower crane. After mould closing and its geometry setting up, a second
geometry control is proceeded taking into previous casted segment geometry. Prior to
concreting, post-tensioning ducts are filled with a rigid pipe in order to prevent any
damage during concreting. After curing, casted segment is shifted nearby the form in
order match the next segment to be concreted. Here below Picture 5 presents the typical
casting sequence for segment prefabrication using match casting.
Step 2:
- Segments rotation & transfer
one by one from trolley
winch to hangers
- Gluing & temporary fixing
of segments with post
tensioning bars
- Segments geometry
adjustment
Step 3:
- Post tensioning installation
- Deck load transfer from
launching girder to piers
Step 4:
- Auxiliary support activation
- Rear support transfer to intermediate pier
- Front support transfer to the next pier
- Gantry self launching on rear & front supports
- Auxiliary support translation to rear support
Picture 8: Erection sequence span-by-span method using launcging girder
The typical cycle achieved using span-by-span erection launching gantry on Dubai red
& green line metro project is on 1,75 day per span. During last month of Red line
construction, 9 units of launching girders was used at the same time on site enabling a
maximum speed of 150 span installed in one month in July 2008.
Step 1:
- Precast pier segment
installation with lorry crane
on pier & with temporary
supports
Step 2:
- Installation of lifting gantry
on pier segment
- Lifting of 1st cantilever
segments with lifting gantry
Step 3:
- Stressing of 1st segment
cantilever tendons
Step 4:
- Launching of lifting gantry
on new installed segment
- Lifting of new segment pair
- Stressing of new segment
installed segment cantilever
tendons
Step 5:
- Repeat step for 3 & 4 for each
new symmetrical segment
- For unbalanced back segment
erection on falsework
Step 5:
- Cast in situ of closure
segment (stitch)
- Installation continuity tendons
The typical cycle achieved using precast segment balanced cantilever construction
method on Dubai red & green line metro project is 4 weeks days for 3 continuous span
deck. Use of classical cast in situ cantilever erection method would lead to 16 weeks
typical cycle duration.
Conclusion
Post tensioned concrete precast segmented bridge technique is an advanced construction
method which provides the following advantages to the project management:
-
All these parameters have participated to reduce the overall project risk for the
contractor, designer and the owner.
10