APC Trainer - Procurement and Tendering Competence (T062) - Online News - Building
APC Trainer - Procurement and Tendering Competence (T062) - Online News - Building
APC Trainer - Procurement and Tendering Competence (T062) - Online News - Building
APC Trainer: Procurement and Tendering competence (T062) | Online News | Building
12/3/13
APC Trainer: Procurement and Tendering competence (T062) | Online News | Building
o Reduced risk of price increases during construction stage, as greater tendering certainty can be achieved through second stage procurement process o Improved programme certainty prior to contract, through early contractor involvement and allowing sufficient time to consider sequencing, lead ins and specialist works o Reduced risk of construction delays due to improved planning during second stage o Potential to transfer a greater degree of design and other construction risk to the contractor o Contractor can help identify and manage risks at an earlier stage ? Contractors : o Costs of abortive tendering significantly reduced o Profitability secured through first stage and costs secured through second stage procurement o Contractor can influence the design, programme and delivery strategy at an earlier stage o Less risk for the contractor as they are able to achieve greater cost and programme certainty prior to committing to a lump sum Disadvantages/ Risks o Unless all packages are firmed up, or the risk is transferred to the contractor, the client will not achieve procurement cost certainty at the end of the second stage and may commence construction with an element of provisional sums to be firmed up post contract o Costs can increase and delays can occur if the contractors design information release requirements are not adhered to by the design team o Additional pre construction costs in the appointment of the contractor o Commitment required to the contractors stage two costs prior to achieving cost certainty on the construction works o Procurement takes longer than single stage and this may delay the start on site date o All advantages can be lost if the team fail to engage and therefore the approach and quality of the consulting and second stage contracting team is essential. o A contractor could take advantage of the second stage negotiations leading to cost increases and a higher than anticipated second stage tender o Potential for failure of the parties to agree the contract sum at the end of stage two, leaving the client open to the risk and cost of re-tendering Lev el 2 Question On your project [X], which was carried out under a two stage procurement approach, what selection criteria was applied in appointing the contractor at stage one? Answer The candidate should be able to draw upon their experience to explain the commercial and technical/ qualitative criteria used, the weighting applied and why these were applied. ? Commercial criteria: o The costs requested from the contractor at stage 1 will vary depending upon the contracting approach, the stage of the project, the information available for the contractor to price and whether any enabling works are required. The
www.building.co.uk/apc-trainer-procurement-and-tendering-competence-(t062)/3110976.article 2/4
12/3/13
APC Trainer: Procurement and Tendering competence (T062) | Online News | Building
costs should be split into stage two and construction stage and would typically include : ? Staff costs ? Overhead and profit ? Allowances for risk ? Design team fees if under a design and build route ? Detailed preliminaries pricing ? The contractor may also be requested to provide a lump sum for enabling works or some early works packages ? Technical criteria would typically include: o Contractors approach to two stage tendering, including commercial considerations, interfacing with the design team and ability to provide value for money o Relevant experience and track record of contractor o Structure and experience of proposed team at each stage o Appropriateness of resource applied to second stage and construction o Understanding the project objectives and constraints and how these will be achieved o Health and safety track record and approach The weighting of the selection criteria should be agreed with the client prior to tender and communicated to all tenderers. It should be heavily weighted towards the technical/ qualitative criteria to obtain best overall value for money from the two stage process. Lev el 3 Question How did you evaluate the stage 1 tender returns and how did you then make your recommendation to the client? Answer The candidate should relate to their actual project in providing the answer to this competency based question, which may include : ? Tender Evaluation : o Tender returns checked for compliance with the invitation to tender o Arithmetical checks carried out on cost components o Any non compliant tenders treated in accordance with the conditions outlined in the Invitation to Tender o All tenders aligned on a like for like basis and compared with each other and the pre tender estimate o Analysis undertaken of resource levels committed by each contractor and on the merits of the team proposed o Post tender interviews carried out with short listed tenderers o Tenders scored against the pre-determined selection criteria ? Tender recommendation report prepared and presented to client, including : o Bid history
www.building.co.uk/apc-trainer-procurement-and-tendering-competence-(t062)/3110976.article 3/4
12/3/13
APC Trainer: Procurement and Tendering competence (T062) | Online News | Building
o Summary of tender returns o Aligned tenders o Scoring of tenders against technical and commercial criteria o Recommendation on what tender represents overall best value for money o Outline of future actions and contracting approach
Postscript:
Dean Mills is a director of Turner & Townsend Building's APC advice is intended as a guideline only and should not replace your own study.
Follow @buildingnews
Tool of Choice for Construction Asta Powerproject is widely used to plan & manage all aspects of the construction lifestyle.
Related Company Resources The latest building ideas & solutions from companies within the industry
Related Company Resources The single resource for all your construction industry needs
ADEBIYI ADEDAYO R. | 28 Apr 08 12:53 pm It is a relevant and useful guide to the profession. Hope to have access to more of this. Thank you.
www.building.co.uk/apc-trainer-procurement-and-tendering-competence-(t062)/3110976.article
4/4