Switch tasks between manual and auto scheduling

Switch tasks between manual and auto scheduling

From the course: Microsoft Project Quick Tips

Switch tasks between manual and auto scheduling

- [Instructor] Switching between manually scheduled and auto scheduled task mode is easy whether you're working with existing tasks or new ones. To switch task mode for an existing task, click its Task Mode cell and click the down arrow that appears. Then choose Manually Scheduled or Auto Scheduled. To switch the task mode for new tasks, on the left side of the status bar, click the button that starts with New Tasks. And then choose the task mode you want for tasks you add in the future. The button displays the task mode after the new tasks label. New tasks you create are set to that task mode, at least until you change it.