Mike Clark

Mike Clark

Canada
9K followers 500+ connections

About

Experienced Construction Professional with a demonstrated history of working in the…

Activity

Join now to see all activity

Experience

Education

Publications

  • PCL One Call

    The Project

    Figure 1. Tower cranes at Project BORR
    Figure 2. Equipment for the wand locator
    Figure 3. Project grid
    Figure 4. Using the Hand held locator
    Figure 5. Locate Tool
    Figure 6. Setting out a locate



    Project BORR is an $833 million design-build project for the Communications Security Establishment Canada. The site is on 84 acres of land and the project will be over 1.3 million square feet. The project comprises several areas, including a parking…

    The Project

    Figure 1. Tower cranes at Project BORR
    Figure 2. Equipment for the wand locator
    Figure 3. Project grid
    Figure 4. Using the Hand held locator
    Figure 5. Locate Tool
    Figure 6. Setting out a locate



    Project BORR is an $833 million design-build project for the Communications Security Establishment Canada. The site is on 84 acres of land and the project will be over 1.3 million square feet. The project comprises several areas, including a parking structure, retail outlet, child-care center, data center, utility building, shipping/receiving building, office pods, and visitor center.

    The Challenge
    With the magnitude of the buried services that needed to be installed on the project, it was necessary to come up with a method for locating the buried services after they were installed. The fact that areas could be re-excavated many times was the motivating force behind the drive to perfect this idea. The size and complexity of the project increased the risk of making contact with underground or overhead services, which can be extremely dangerous and significantly affect the cost and schedule. Time was also a factor in obtaining locates for a project of this size.

    Requesting locates from multiple locating companies can be a lengthy process that is determined by their availability and turnaround times. The project required a system that would be effective over the 36 months during which various types of excavating would occur.

    The challenge was to create a system that minimizes accidental contacts and rework to underground and overhead services in order to increase safety, decrease cost, and help maintain the schedule.

    For more information Contact Mike Clark

  • The Store

    The Project
    Project BORR is an $833 million, secured government facility located in Ottawa, Canada. The project consists of an 84-acre site with 1.3 million square feet of usable space. The facility consists of a main office complex, data center, shipping and receiving building, parking structure, visitors center, and a bank/daycare building.

    The Challenge

    Figure 1: Overall site view

    Figure 2: Material security screening.

    Figure 3: Loading area at the…

    The Project
    Project BORR is an $833 million, secured government facility located in Ottawa, Canada. The project consists of an 84-acre site with 1.3 million square feet of usable space. The facility consists of a main office complex, data center, shipping and receiving building, parking structure, visitors center, and a bank/daycare building.

    The Challenge

    Figure 1: Overall site view

    Figure 2: Material security screening.

    Figure 3: Loading area at the Store.


    Figure 4: Storage in the laydown yard.
    The challenge was finding a logistics solution that met security requirements and organizational demands a project of this size creates on the supply chain. The project agreement dictated that all material and equipment deliveries needed to run through a single security screening process.

    The Solution
    The Store is the security checkpoint facility located directly behind the main project entrance. It provides a controlled means of managing, coordinating, and tracking materials, equipment, tools, and expendables for PCL’s construction activities. Subcontractors also used the Store to coordinate their site deliveries; they were responsible for their own ordering, delivery within site, and laydown.

    All PCL staff followed a detailed procedure for procurement, and subcontractors followed the site delivery procedures. These procedures specified that all delivery personnel be prescreened so that they could access the secure site.

    Received materials were subject to security protocols, which became more and more stringent as the project progressed as the sensitivity of goods being delivered increased. Essentially all materials, equipment, and services were scrutinized by hired security personnel, who then contacted the material control group once the materials were cleared. Afterward, the goods were marshaled to a designated area in the laydown yard, awaiting final disposition.

  • Metal Stud Elevator Door Framing vs. Masonry Supported Door Frames

    Mike Clark

    The Solution
    To come up with an elevator framing solution that would reduce the long duration to complete the elevator lobbies.

    The alternate solution was to frame the elevator frames with metal stud (each project needs to be analyzed by an engineer for stud sizing and spacing).

    The elevator frames are installed from the lowest to the highest floors. The metal framing can follow this process, as there is no need to clean the equipment by the elevator contractor, thus…

    The Solution
    To come up with an elevator framing solution that would reduce the long duration to complete the elevator lobbies.

    The alternate solution was to frame the elevator frames with metal stud (each project needs to be analyzed by an engineer for stud sizing and spacing).

    The elevator frames are installed from the lowest to the highest floors. The metal framing can follow this process, as there is no need to clean the equipment by the elevator contractor, thus eliminating the cost to employ the elevator contractor to do so. The elevator contractors can typically install the frames, at 2 floors/day, as before, with a net result of 25 scheduled days.

    The drywall contractor can stay up with the elevator contractor, and complete the framing 2 days after the elevator contractor. This would mean an additional two days on the schedule duration, of a net 27 days to this point.

    The real benefit now comes with the elevator lobby framing that can begin once the elevator frames are secured. This activity can begin in conjunction with the door framing. The net result of this flow of activity has the elevator lobbies completed approximately 52 schedule day’s earlier than the previous method

    Contact Mike for the Full Report

  • High Rise Mechanical Penthouse Structure Reinforced Concrete vs. Structural Steel

    Mike Clark

    .

    The Solution
    One way to mitigate problems with the reinforced concrete method was to pour the roof structure, elevator core and machine room structure, pour the equipment pads, and turn the structure over to the steel erectors. The steel erectors could complete the structure in a fraction of the time and were not as averse to the weather conditions as the forming crews were.

    The building mechanical and electrical equipment could be preloaded into the space, without any…

    .

    The Solution
    One way to mitigate problems with the reinforced concrete method was to pour the roof structure, elevator core and machine room structure, pour the equipment pads, and turn the structure over to the steel erectors. The steel erectors could complete the structure in a fraction of the time and were not as averse to the weather conditions as the forming crews were.

    The building mechanical and electrical equipment could be preloaded into the space, without any interference from the false work or shoring systems that the cast-in-place structure would require. The steel and cladding could be predesigned for a seamless fit. The cladding and/or concrete often need to be modified with the concrete cast-in-place system. The use of structural steel, on the other hand, made access to the space safer and easier to work around, once the structure was complete.

    The penthouse equipment can be worked on earlier, allowing for the building systems to be turned on sooner. When the “Top of House” gets completed, any inner tower crane can be removed from the building.

    Once the tower crane is removed, the roofing can be completed to create a watertight building. Structural steel is cleaner and takes up less space than the conventional forms required for the cast-in-place structure. The steel comes in on a trailer and is hoisted directly into place, whereas forms must be stored on the ground, lifted into place, and then stripped and possibly reused. This requires a lot of crane time, and site space for the material.

    Structural steel construction allows for the envelope to be installed earlier, helping to expedite getting the building watertight. Once the tower crane is removed, the re-shoring can also be removed and the floors finished.

    Contact Mike for the Full Report

  • Retractable Climbing Syatem for High Rise Buildings

    Mike Clark

    The Solution
    The suppliers at a 50-story high-rise project in Chicago had installed a perimeter panel protection system that worked with knock-down forming assemblies. The perimeter panels provided high vertical walls that enclosed the working/forming deck and false work floor, and were also used at the trailing reshore floor.

    This perimeter panel blocked wind substantially, therefore decreasing the frequency of job site closure.

    The team considered how the perimeter panels…

    The Solution
    The suppliers at a 50-story high-rise project in Chicago had installed a perimeter panel protection system that worked with knock-down forming assemblies. The perimeter panels provided high vertical walls that enclosed the working/forming deck and false work floor, and were also used at the trailing reshore floor.

    This perimeter panel blocked wind substantially, therefore decreasing the frequency of job site closure.

    The team considered how the perimeter panels could be incorporated with a self-climbing formwork system that would still allow the access needed to move the flyforms between floors. No off-the-shelf system was available, so a prototype was developed.

    The formwork contractor, system engineer, developer, and the engineer of record for the building contributed to coordinating the perimeter panel system. Since it was a new system not included in the original bid, the supplier, contactor, developer/owner, and PCL negotiated to split its cost.

    The concrete floor slab work on the site was done on a three-day forming cycle. The three days include time to set the forms and shores, pour the concrete, strip the forms and shores from a floor below, and start a new cycle on another floor above.

    The perimeter panel system that was finally built was a modified self-climbing core form system. It had the added ability to flip a wall section out, which allowed the site tower crane to roll out the flyforms. The self-climbing aspect of the system allowed it to be raised up to additional floors without taking up valuable tower crane time.

    A preliminary concern was that the system would slow down the schedule cycle, and consequently negate the advantage of wind blocking. Before the perimeter panel system was added to the production cycle, therefore, it was site tested to identify any potential disruption to the schedule. So when forming began on the 10th floor of the main structure,

    Contact Mike for the Full Report

  • Temporary Concrete Access Ramp

    Mike Clark

    The Solution
    During the pursuit stage of the project, the project team devised a method of building a highway ramp that would cut through the site, allowing the loading dock to remain active while the new ramp was constructed as per the original building design. Implementation of the ramp design was subject to many logistical and structural engineering considerations. The ramp needed to withstand heavy highway loads. It also had to be constructed in such a way that it would not interfere…

    The Solution
    During the pursuit stage of the project, the project team devised a method of building a highway ramp that would cut through the site, allowing the loading dock to remain active while the new ramp was constructed as per the original building design. Implementation of the ramp design was subject to many logistical and structural engineering considerations. The ramp needed to withstand heavy highway loads. It also had to be constructed in such a way that it would not interfere with the permanent ramp. Finally it would need to be dismantled as the permanent tower structure was built around it. The decision was made to curl the ramp from the loading dock through the podium and up onto the side street directly in front of the Air Canada Centre. This would allow the project team to fast track the building of the permanent ramp, so the temporary ramp could be removed in time for construction to begin on the high rise, without any changes to the overall project schedule

    Contact Mike for the full report

Honors & Awards

  • Toronto Construction Association "Best of the Best"

    -

    Winner of the "Best of the Best" for Medium size Project for Palisades on the Glen

  • • Toronto Construction Association "Best of the Best"

    -

    PCL was selected as the Toronto Construction Associations 2005 winner of the “Best of the Best” Award – Outstanding Safety Performance for our work on the Harbour View Estate project. A significant accomplishment was achieving 1,000,000 man-hours without a Lost Time Injury, a first for a residential project in Ontario.

  • 2011 Corporate Innovation Award

    PCL

    2011 Innovation Awards


    --------------------------------------------------------------------------------



    Page Content
    ​The PCL family of companies is pleased to announce the 2011 Innovation Award winners. These teams serve as great examples of the people in our organization who are finding creative ways to work safer, faster, and more efficiently every day, to produce a quality product.

    “Innovation,” says Paul Douglas, president and CEO, “helps…

    2011 Innovation Awards


    --------------------------------------------------------------------------------



    Page Content
    ​The PCL family of companies is pleased to announce the 2011 Innovation Award winners. These teams serve as great examples of the people in our organization who are finding creative ways to work safer, faster, and more efficiently every day, to produce a quality product.

    “Innovation,” says Paul Douglas, president and CEO, “helps drive PCL’s success, and the QUEST bulletin program allows PCLers to show their resourcefulness in meeting challenges on the job. I thank all contributors to the program, and congratulate this year’s winners; putting your ideas into practice will help bring improvements to safety, quality, and productivity at PCL for years to come.”

    One thousand dollars will be shared amongst the team who submitted the winning idea for each of the three innovation awards.




    Retractable Climbing System for Wind Protection
    Submitted by: Fernando Tito, Peter Olive, Scott Wood, Mike Jones, Mike Clark (PCL Constructors Canada Inc., Toronto)

    More time on a high-rise structure is lost to wind than to all other weather conditions combined. The team showed perseverance and innovation by making an existing idea more efficient and effective; they developed a prototype that took an existing perimeter panel protection system, made it self-climbing, and implemented a landing platform. The self-climbing aspect of the system allowed it to be raised up to other floors without a tower crane. Subsequent worldwide use of the system has created enduring benefits for PCL’s industry reputation.

More activity by Mike

View Mike’s full profile

  • See who you know in common
  • Get introduced
  • Contact Mike directly
Join to view full profile

Other similar profiles

Explore collaborative articles

We’re unlocking community knowledge in a new way. Experts add insights directly into each article, started with the help of AI.

Explore More

Others named Mike Clark in Canada

Add new skills with these courses